In the early stages of a hotel development study, zoning, floor-area ratio and the parking-provision requirement always get checked. There is one more condition beyond them, in force since April 2025: the EV charging equipment installation mandate Tokyo imposes on new buildings. It comes from a revision to the Tokyo Metropolitan Ordinance on Environmental Preservation (the Environmental Security Ordinance), passed by the Metropolitan Assembly in December 2022, and it reaches new construction with a total floor area of 2,000 m² or more through the Tokyo Green Building Program.

What makes this mandate unusual is that it is triggered not by floor area or room count but by the number of parking spaces. The number of spaces required under the parking ordinance directly determines whether chargers are needed and how many. This article first confirms Tokyo’s installation standard against primary sources, then works backwards from our building-plan data and the parking ordinance unit rate to answer the question of what room count brings a hotel into scope, and costs out the three Capex layers — chargers, pre-installed conduit and incoming power capacity — for 100-room and 300-room models. Taking subsidies and charging revenue in as well, the aim is to quantify one more layer of development cost: electrical infrastructure.

Metric Definitions Used in This Article

  • Charging equipment: equipment covered by the EV charging equipment installation standard under the Tokyo Green Building Program. This article costs out 6 kW standard (Level 2) chargers as the base case.
  • Conduit and related work: work that reserves conduit, wiring space and distribution-board headroom in advance so chargers can be added later — what is generally called EV-ready provision.
  • Dedicated parking / shared parking: the categories used in Tokyo’s installation standard. Dedicated parking is space contracted for exclusive use by specific users (residents, company vehicles and the like); shared parking serves visitors, with a shifting mix of vehicles and short stays. A hotel’s guest parking falls under shared parking.
  • Parking-provision requirement: the obligation to provide parking facilities set by each local government by ordinance under Article 20 of the Parking Place Act. Under the Tokyo Metropolitan Parking Ordinance, the current unit rate for hotels and ryokan in parking improvement districts and similar areas is one space per 300 m².
  • ADR (average daily rate): an estimated settled rate (tax-excluded equivalent) calculated by applying a segment-specific adjustment factor to the lowest published plan level each property lists on OTAs and elsewhere (double occupancy, per-room rate, tax included). Against property-level results disclosed by listed hotel REITs (91 properties, most recent three months), the median error is about 7%. These are estimates and differ from each property’s actual transaction prices and accounting figures. Area-level ADR is the median across the properties covered (the level of a typical property in that area).
  • Data sources: Tokyo Metropolitan Government Bureau of Environment / Tokyo Metropolitan Government Bureau of Urban Development / Ministry of Land, Infrastructure, Transport and Tourism, Statistical Survey on Building Construction Starts, compiled by MetroEngines Research & Consulting / MetroEngines Research
Room count at which the mandate bites
About 140 rooms
Back-calculated at the current 300 m²/space rate
Under the proposed revision
About 180 rooms
At 450 m²/space the threshold moves back
Planned hotels in Tokyo
18 projects
All above 2,000 m² floor area, 3,497 rooms in total
Capex, 300-room model
¥0.78M–19.32M
The range turns on capacity upsizing
Burden per room-night
¥0.6–14.7
15-year depreciation, 80% occupancy
Key Takeaways
  • — The mandate is triggered not by floor area or room count but by the number of parking spaces. Guest parking counts as shared parking: 10 spaces or more means one charger plus conduit for 20% of spaces. Dedicated parking for employees and company vehicles starts at 5 spaces, with chargers on 20%.
  • — Working back from the Tokyo Metropolitan Parking Ordinance, a hotel in a central commercial district enters scope at about 140 rooms (total floor area above 3,525 m², at 25 m² per room). A 100-room property stays outside scope because the relief formula applies.
  • — Capex for the 300-room model is ¥780,000 to ¥19.32 million. Chargers and conduit alone come to ¥780,000–¥4.32 million, or ¥0.6–3.3 per room-night — not a scale that decides project viability.
  • — The width of that range comes down to incoming power capacity. Upsizing the substation puts the figure in the ¥15 million class, and that portion sits outside subsidy coverage. The outcome is all but decided at the load-calculation stage of schematic design.
  • — If the proposed parking ordinance revision published in June 2026 (unit rate from 300 to 450 m² per space) is enacted, the trigger point moves back from about 140 rooms to about 180 rooms. The ordinance revision has not been enacted.

A mandate triggered by parking spaces, not floor area

Tokyo’s Metropolitan Assembly passed the revision to the Environmental Security Ordinance on 15 December 2022, making solar generation equipment and EV charging equipment part of the rules for new buildings. Both took effect in April 2025. We have covered the solar side before; the charging side is often still missing from development planning templates.

What applies to large new buildings of 2,000 m² or more is the EV charging equipment installation standard under the Tokyo Green Building Program, and the requirement splits in two depending on the character of the parking. That split is the practical dividing line.

Table 1. Tokyo’s EV charging equipment installation standard (new buildings of 2,000 m² or more, by parking category)
CategoryParking spaces at which it appliesChargers to installConduit and related work
Dedicated parking
Specific spaces contracted for exclusive use (company vehicles, employees and the like)
5 or more20% or more of spaces
capped at 10
50% or more of spaces
capped at 25
Shared parking
Visitors, shifting mix of vehicles, short stays. Hotel guest parking belongs here
10 or more1 or more20% or more of spaces
capped at 10

Source: Tokyo Metropolitan Government Bureau of Environment, Guideline on the EV Charging Equipment Installation Standard under the Tokyo Green Building Program (1st edition, March 2024) / Tokyo Metropolitan Ordinance on Environmental Preservation. The guideline is split by submission period: the 1st edition applies to submissions from April 2025 to March 2026, the 2nd edition to submissions from April 2026 onward.

The rule is often described as chargers on 20% of the parking, but the 20% applies to dedicated parking. Hotel guest parking, with its shifting mix of vehicles and short stays, is classified as shared parking: at 10 spaces or more, at least one charger is required, plus pre-installed conduit for 20% or more of the spaces. Where contracted spaces are allocated to employees or company vehicles, the 20% rule kicks in once those spaces number five or more. In other words, two standards run in parallel inside the same building.

Below 2,000 m², a separate track applies: the Green Building Report Program, also in force since April 2025. It covers designated suppliers that deliver 20,000 m² or more of small and mid-sized new buildings in Tokyo per year, and the obligation attaches to the supplier rather than to the individual building. Chains that keep delivering compact hotels in Tokyo should note they may fall within its reach.

We also checked other local governments. Kawasaki has run a solar generation programme since April 2025, but within the scope of this study we found no programme setting a numerical requirement for charger counts. Nagano Prefecture asks new buildings of 10,000 m² or more to consider installing renewable energy equipment, but that is a duty to consider, not to install. On numerical charger requirements for new buildings, Tokyo is ahead of the field at this point. For developers working in Kyoto or Osaka, the near-term question is mainly which subsidies to use.

At what room count does a hotel enter scope — working back from the parking requirement

Whether chargers are required is decided by the number of parking spaces. So what decides a hotel’s parking space count? In Tokyo, the provision requirement under the Tokyo Metropolitan Parking Ordinance effectively sets the floor. In parking improvement districts and similar areas, the unit rate for hotels and ryokan is one space per 300 m² (we compared seven cities on this point in earlier work: hotel parking provision requirements differ by a factor of 2.5 across cities).

Using the same assumptions as that study (300 rooms, 7,500 m² total floor area, or 25 m² per room) and assuming the number of spaces actually provided equals the required number, we tested where the mandate bites by property size. Ten shared-parking spaces is the dividing line.

Source: compiled by MetroEngines Research & Consulting from the Tokyo Metropolitan Parking Ordinance and the Bureau of Environment installation standard

Table 2. Required parking spaces and charging mandate by room count (current unit rate / proposed revision)
RoomsTotal floor areaRequired spaces
current, 300 m²/space
Charging mandate (current)Required spaces
proposed, 450 m²/space
Charging mandate (proposed)
100 rooms2,500 m²5Not covered3Not covered
150 rooms3,750 m²101 charger + conduit for 2 spaces7Not covered
200 rooms5,000 m²161 charger + conduit for 4 spaces111 charger + conduit for 3 spaces
300 rooms7,500 m²251 charger + conduit for 5 spaces171 charger + conduit for 4 spaces
500 rooms12,500 m²421 charger + conduit for 9 spaces281 charger + conduit for 6 spaces

Assumes 25 m² of floor area per room and that required spaces equal the spaces actually provided. Below 6,000 m² the ordinance relief formula applies, rounded up. The provision requirement covers parking improvement districts, commercial zones, neighbourhood commercial zones and similar areas. Source: compiled by MetroEngines Research & Consulting from the Tokyo Metropolitan Parking Ordinance and the Bureau of Environment

Solving the threshold precisely means folding in the relief formula that applies below 6,000 m². For a hotel-only building the required space count is (4 × total floor area − 6,000) ÷ 900, so rounding up, it reaches 10 spaces at a total floor area above 3,525 m² — at 25 m² per room, about 140 rooms. Under the current standard, a new hotel above roughly 140 rooms in a central Tokyo commercial district triggers the charger installation requirement. A 100-room property stops at five spaces thanks to the relief formula and stays outside scope.

Worth watching here is the Basic Approach to Revising the Tokyo Metropolitan Parking Ordinance (draft), published by the Bureau of Urban Development on 8 June 2026. It would ease the unit rate for other designated uses, a category that includes hotels, from 300 m² per space to 450 m² per space, and public comment ran to 8 July of the same year (the ordinance revision has not been enacted). If it goes through, the lower required space count means the charging mandate’s trigger point also moves back from about 140 rooms to about 180 rooms. Because the parking ordinance and the charging mandate are numerically linked, easing one eases the other. Projects filing for building confirmation in 2026 and 2027 will be planned while both rules are in motion — worth pinning down at the planning stage.

All 18 planned Tokyo projects exceed 2,000 m²

Extracting planned and under-construction projects that include a hotel in Tokyo from the building-plan data we maintain from the Ministry of Land, Infrastructure, Transport and Tourism’s Statistical Survey on Building Construction Starts gives 18 projects and 3,497 rooms (after de-duplication, as of the survey date). Of these, all 18 are at 2,000 m² or more, putting them within the Tokyo Green Building Program’s scope. Nationwide, 62 of 69 projects (89.9%) were at 2,000 m² or more.

By ward, Chiyoda leads with 5 projects and 728 rooms, followed by Shibuya with 3 projects and 461 rooms and Minato with 2 projects and 417 rooms. Projects in Chiyoda, Minato, Chuo and Shinagawa include mixed-use redevelopments with office and retail space running to several hundred thousand square metres, where charger placement is decided within the whole building’s parking plan rather than the hotel portion alone.

Note on the data
This data is based on building confirmation filings as of the survey date (Ministry of Land, Infrastructure, Transport and Tourism, Statistical Survey on Building Construction Starts). Because confirmation filings are typically made one to two years before opening, project and room counts for future years are expected to rise as further filings come in. Treat the figures as a lower bound on the confirmed pipeline.

Markers are placed at ward office locations as an approximate ward-level display, not the exact site of each project. Circle size is the total planned room count in that ward. Source: compiled by MetroEngines Research & Consulting from the Ministry of Land, Infrastructure, Transport and Tourism’s Statistical Survey on Building Construction Starts (N=18 projects)

Separately, for the nine Tokyo projects that are hotel-only and have a reported total floor area, applying the current unit rate and the relief formula gives required space counts of 4.8 to 19.8 spaces. Six of the nine reach 10 or more once rounded up. That said, floor areas in building-plan data are as filed, and the actual required count moves with how the parking portion is treated and which relief measures apply. Determinations on individual projects presuppose consultation with the competent authority.

Capex splits into three layers

Charging Capex cannot be expressed as a single number. Stacking it in three layers — (1) the chargers themselves, (2) pre-installed conduit, (3) incoming power capacity — shows where the range comes from.

(1) Chargers. Material submitted by the Bureau of Urban Development to the parking ordinance review committee (based on operator interviews) puts the initial cost of a fast charger at about ¥2 million to ¥3 million per unit, with a service life of about eight years. What is realistic for hotel guests is a 6 kW standard charger used during the stay, where equipment and installation together run from several hundred thousand yen up to around ¥2 million in difficult conditions. Tokyo’s subsidy caps installation work for the first standard charger at ¥1.35 million, which gives a sense of the ceiling on the works side.

(2) Conduit. Installing conduit routes, wiring and distribution-board headroom at the same time as new construction adds ¥10,000 to ¥40,000 per space. That is far cheaper than retrofitting — opening walls, adding distribution boards, redoing buried conduit — so running conduit to more spaces than the mandate requires compresses later Capex. The 300-room model needs 8 spaces (5 shared plus 3 dedicated), but running conduit to all 25 spaces adds only a few hundred thousand yen.

(3) Incoming power capacity. This is what sets the width of the range. Load density in hotel electrical design generally runs 50 to 80 VA/m², so a 300-room, 7,500 m² building implies 375–600 kVA of substation capacity. Adding 6 kW × 2 units, or 12 kW, to that is only 2.0–3.2% of the incoming capacity, which usually sits inside normal design headroom. The problem case is converting all eight mandated conduit spaces to chargers in future: at 48 kW the ratio rises to 8–13%. If the design was laid out without headroom, transformers or the cubicle substation have to be upsized, and unit prices of ¥8 million to ¥15 million for 300–500 kVA class equipment — around ¥15 million for a full replacement job — come into view.

Source: compiled by MetroEngines Research & Consulting from Tokyo Metropolitan Government Bureau of Urban Development, Guiding the installation of ZEV chargers under the parking ordinance / Tokyo Metropolitan Environmental Public Service Corporation subsidy programmes / prevailing price ranges for substation equipment

Table 3. Charging Capex for the 300-room model (by layer, low and high case)
LayerQuantity in the 300-room modelLowHigh
Chargers (6 kW standard)1 shared + 1 dedicated = 2 units¥0.70M¥4.00M
Pre-installed conduit5 shared + 3 dedicated = 8 spaces¥0.08M¥0.32M
Incoming power capacity+12 kW (no increment if within design headroom)¥0¥15.00M
Total¥0.78M¥19.32M
Per room¥26,000¥64,000
Per room-night (15-year depreciation, 80% occupancy)87,600 room-nights a year¥0.6¥14.7

A simplified estimate; an actual investment decision requires a detailed feasibility study. Source: MetroEngines Research & Consulting

Separating where the range comes from shows that what matters is not the amount itself but how incoming power capacity is handled. Below, an optimistic and a mid case that stop at chargers and conduit sit alongside a pessimistic case that includes upsizing the substation.

Table 5. Three scenarios for the 300-room model — the burden range set by how power capacity is handled
ScenarioAssumptionsTotal CapexPer roomPer room-nightShare of estimated settled ADR
OptimisticNo capacity upsizing, equipment at the low end (2 chargers ¥0.70M + conduit for 8 spaces ¥0.08M)¥0.78M¥26,000¥0.60.004%
MidNo capacity upsizing, equipment at the high end (2 chargers ¥4.00M + conduit for 8 spaces ¥0.32M)¥4.32M¥14,400¥3.30.023%
PessimisticSubstation upsizing required (cubicle replacement of ¥15.0M added)¥19.32M¥64,400¥14.70.104%

Straight-line depreciation over 15 years, 80% occupancy (87,600 room-nights a year for 300 rooms). The ADR share is against the trailing-12-month median estimated settled ADR for business hotels in Tokyo of ¥14,100 (N=910 properties). Figures are before subsidies. Source: Tokyo Metropolitan Government Bureau of Urban Development / Tokyo Metropolitan Environmental Public Service Corporation / compiled by MetroEngines Research & Consulting

Laying the per-room-night burden out on two axes — the cost of upsizing capacity and the room count — makes clear that the weight falls hardest on smaller properties. The same ¥15 million of upsizing works out at ¥8.8 per room-night for 500 rooms but ¥29.4 for 150 rooms, a gap of more than three times. The smaller the project, the more it is worth folding the charging load into the load calculation at schematic design.

Table 6. Sensitivity — effect of upsizing cost and room count on the burden per room-night (¥)
Upsizing cost / rooms150 rooms200 rooms300 rooms500 rooms
¥0
within design headroom
6.64.93.32.0
¥5.0M14.210.67.14.3
¥10.0M21.816.310.96.5
¥15.0M
cubicle replacement
29.422.114.78.8

Chargers plus conduit are fixed at the 300-room model’s high case of ¥4.32M, with size differences reflected only in the depreciation denominator — a conservative treatment. Straight-line depreciation over 15 years, 80% occupancy. The shaded cell matches the ¥14.7 per room-night in the text (300 rooms, ¥15.0M upsizing). Even the heaviest cell, 150 rooms with ¥15.0M, stays at ¥29.4, or 0.21% of the ¥14,100 estimated settled ADR. Source: compiled by MetroEngines Research & Consulting

In short, where no capacity upsizing is required, this mandate’s effect on project viability is very small. Our aggregation puts the trailing-12-month median estimated settled ADR for business hotels in Tokyo at about ¥14,100 (N=910 properties), against which ¥0.6–14.7 per room-night is 0.004% to 0.10% of ADR. Set against the water connection charges we have covered before (a gap of up to ¥5.11 million between municipalities) or the Capex arising from parking provision requirements (¥140,000–350,000 per room), it is an order of magnitude smaller. Rather than the amount itself, at what point it is folded into the substation plan is the design-process question that matches reality.

Running cost is set by the base charge and maintenance

More deserving of attention than Capex is the running cost. The same Bureau of Urban Development material shows, for a fast charger (50 kW output, low-voltage power contract), an electricity base charge of about ¥50,000 a month, or about ¥600,000 a year, network fees of about ¥4,000 to ¥5,000 a month and maintenance and inspection of about ¥300,000 a year — about ¥1 million a year in total, excluding the electricity used for charging. The same material notes that recovering installation costs from charging fees alone is difficult, and that installation does not proceed unless secondary effects such as drawing customers are expected.

That, however, is the figure for a 50 kW fast charger. Scaled proportionally to the two 6 kW standard chargers, or 12 kW, that are central to a hotel’s compliance, the equivalent base charge is only about ¥140,000 a year (our estimate). Adding network fees and maintenance keeps it in the range of a few hundred thousand yen a year, which across 300 rooms and 87,600 room-nights is a few yen per room-night. Whether a fast charger goes in as destination charging is the fork that shifts Opex to a different level.

Source: compiled by MetroEngines Research & Consulting from Tokyo Metropolitan Government Bureau of Urban Development, Guiding the installation of ZEV chargers under the parking ordinance (the 12 kW figures are our estimate, scaled proportionally from prevailing 50 kW values)

How far do subsidies bring the net burden down?

Two tracks of support exist, national and metropolitan. The national subsidy for the introduction of charging and refuelling infrastructure to promote clean energy vehicles is administered by the Next Generation Vehicle Promotion Center, and accommodation facilities are included among eligible sites. For standard chargers, the framework covers up to half of equipment purchase costs and the full installation cost.

Tokyo’s side splits in two: the Charging Equipment Deployment Program (residential), for apartment buildings and municipal public facilities, and the Charging Equipment Deployment Program (business), for retail, office and industrial facilities. Under the latter, half of the purchase cost of a standard charger is covered, installation work is capped at ¥1.35 million for the first unit, and for fast chargers (10 kW or more) and ultra-fast chargers (90 kW or more) the purchase cost is fully covered, with per-model caps, and installation is capped at ¥62,000/kW and ¥80,000/kW respectively. Applications run from 26 June 2026 to 31 March 2027. Which programme category a project falls under is worth confirming with the administering office before applying.

Table 4. Main subsidies available for standard chargers (FY2026)
ProgrammeAdministratorEligible sitesSupport for standard chargers
Charging and refuelling infrastructure subsidyNext Generation Vehicle Promotion Center (national)Apartment buildings, workplaces, retail facilities, accommodation facilities and similarUp to 1/2 of purchase cost, full installation cost
Charging Equipment Deployment Program (business)Tokyo Metropolitan Environmental Public Service CorporationRetail, office and industrial facilities1/2 of purchase cost, installation capped at ¥1.35M for the first unit
Charging Equipment Deployment Program (residential)Tokyo Metropolitan Environmental Public Service CorporationApartment buildings and municipal public facilities1/2 of purchase cost, installation capped at ¥1.35M for the first unit

Based on FY2026 published terms. Budgets, application windows and requirements change each fiscal year, so always check the latest application guidelines when applying. Source: Next Generation Vehicle Promotion Center / Tokyo Metropolitan Environmental Public Service Corporation (Cool Net Tokyo)

With subsidies folded in, the two chargers in the 300-room model attract half the purchase cost plus support equivalent to the installation cost, so the net burden in the low case falls to a few hundred thousand yen. Put the other way, the ¥15 million in the case that needs capacity upsizing sits outside subsidy coverage, so most of the net burden is decided on the substation side. Whether the charging load can be folded into the load calculation early in design is exactly what the difference in net burden comes down to.

The revenue side — charging income and capturing EV drivers

So far the cost side, but chargers have revenue potential too. Japan’s EV and PHEV share of new car sales reached 5.48% in June 2026, up 2.57 points from 2.91% a year earlier and a record high. The government targets 100% electrified vehicles in new passenger car sales by 2035 and 300,000 charging points by 2030, including 30,000 public fast chargers. Accommodation facilities are positioned as a principal site for destination charging, and the long dwell times of the business suit 6 kW standard charging. Where EV charging at regional lodgings is concentrated, as seen in guest reviews, is analysed in our earlier work.

A look at charging revenue. Prevailing time-based pricing for standard charging runs around ¥55 per 10 minutes, so a three-hour charge during a stay comes to about ¥990. At one use per unit per day, that is about ¥360,000 a year per unit, or ¥720,000 for two. That exceeds the Opex seen in the previous section (about ¥140,000 of base charge for 12 kW plus network fees and maintenance). Even in a ramp-up period short of one use a day, it covers more than half of Opex.

Value also varies with whether parking itself is valued in the local market. In our map of parking mention rates in guest reviews, Tokyo’s mention rate is a low 2.0%, while regional cities with weak rail connectivity exceed 10%. Building know-how first through Tokyo compliance, then carrying it across to projects in markets where parking is valued is a sensible order for chains. The field also connects to inbound rental-car demand: our analysis of inbound rental-car demand and parking mentions found parking mentioned 2.9 times more often in Traditional Chinese reviews than in English.

Conclusion — a question of design sequence, not amount

Summed up from a development-planning perspective, Tokyo’s EV charging equipment mandate comes to this.

First, the mandate is triggered by parking spaces, not floor area or room count. A hotel’s guest parking is shared parking: at 10 spaces or more, at least one charger and conduit for 20% or more of the spaces are required. The chargers-on-20% line applies to dedicated parking for employees and company vehicles, which comes into scope at five spaces.

Second, working back from the parking provision requirement, a hotel in a central commercial district enters scope at about 140 rooms. If the parking ordinance revision published in June 2026 (unit rate from 300 to 450 m² per space) is enacted, that threshold moves back to about 180 rooms. Because the two rules are numerically linked, projects filing for building confirmation in 2026 and 2027 need to watch both at once.

Third, Capex ranges widely, from ¥780,000 to ¥19.32 million, but the width comes from incoming power capacity. Chargers and conduit together come to ¥780,000–¥4.32 million, or ¥0.6–3.3 per room-night — not a scale that decides viability. Once the substation has to be upsized, however, the figure moves into the ¥15 million class, and that portion falls outside subsidy coverage. The outcome is all but decided when the charging load is folded into the load calculation at schematic design.

Fourth, there is clear upside in running conduit to more spaces than the mandate requires. At ¥10,000 to ¥40,000 per space when installed with new construction, running it to all 25 spaces in the 300-room model adds only a few hundred thousand yen. With the EV share of new car sales rising more than two points a year, it avoids the cost of opening walls and redoing conduit at a later renovation. Leaving future headroom in the substation as well keeps the option of pursuing charging revenue open.

We have quantified the infrastructure costs that tend to fall out of business-plan templates one by one — water connection charges, water and sewer costs, waste disposal costs. Electrical infrastructure is the smallest of them in money terms, yet the layer that gets locked in earliest in design. Noticed just before the confirmation filing, there are no options left; folded into schematic design, it costs a few hundred thousand yen — that asymmetry is precisely why this layer belongs on the planning-stage checklist.

Related Reading

References and Sources

■ Data sources

Regulatory requirements come from the Tokyo Metropolitan Government Bureau of Environment’s EV charging equipment installation standard and the Tokyo Metropolitan Ordinance on Environmental Preservation; required parking counts from the unit rate in the Tokyo Metropolitan Parking Ordinance (hotels and ryokan, 300 m² per space; proposed 450 m² per space). Planned and under-construction projects come from building-plan data derived from the Ministry of Land, Infrastructure, Transport and Tourism’s Statistical Survey on Building Construction Starts (after de-duplication, N=69 projects, of which 18 in Tokyo with 3,497 rooms, as of the survey date). Estimated settled ADR is the trailing-12-month median of monthly aggregates for business hotels in Tokyo (N=910 properties, September 2025 to August 2026). Equipment, installation and running costs come from the Bureau of Urban Development’s parking ordinance review committee materials; subsidies from the published guidelines of the Next Generation Vehicle Promotion Center and the Tokyo Metropolitan Environmental Public Service Corporation.

■ Estimation assumptions

Assumes 25 m² of floor area per room and that the required parking count equals the spaces actually provided. Below 6,000 m², the Tokyo Metropolitan Parking Ordinance relief formula (4 × total floor area − 6,000) ÷ 900 applies, rounded up. Chargers are 6 kW standard units as the base case; the 300-room model takes 1 shared + 1 dedicated = 2 units, with conduit for 5 shared + 3 dedicated = 8 spaces as the mandated level. Capex is converted to a per-room-night figure on straight-line depreciation over 15 years at 80% occupancy (87,600 room-nights a year for 300 rooms). In the sensitivity table, chargers plus conduit are fixed at the high case of ¥4.32M and size differences are reflected only in the depreciation denominator, a conservative treatment for smaller projects. The 12 kW running-cost equivalent is our estimate, scaled proportionally from prevailing 50 kW values.

■ Limitations and caveats

Final determinations on required parking counts, and on whether and how many chargers are needed, are made in consultation with the competent authority and vary with how parking area is counted and which relief measures apply. Floor areas in building-plan data are as filed at confirmation, and for mixed-use projects the hotel portion cannot be separated from the whole building. Whether capacity upsizing is needed depends on each project’s load calculation and existing design headroom, so the Capex range here is an indicative upper and lower bound, not a budget for any specific project. Subsidy budgets, application windows and requirements change each fiscal year. As of September 2026 the parking ordinance revision has completed public comment; the ordinance revision has not been enacted. Estimated settled ADR is an estimate and differs from each property’s actual transaction prices and accounting figures.

■ Regulations and primary sources

■ Subsidies

■ Market data

Related Articles

  • JNTO Announces March 2026 Foreign Visitor Arrivals to Japan Reached 3,618,900, Up 3.5% Year-on-Year and a Record High for March

  • Golden Week 2026 Hokkaido Hotel Price Analysis: Niseko +29% and the Drivers Behind the Surge in Sell-Out Rates

  • Post-Golden Week Hotel Prices Drop Up to 44%: Why Mid-May Is the Best Time to Book

  • Golden Week 2026 Hotel Price YoY Analysis Across Six Major Cities: Unpacking the Drivers Behind Kyoto (+20%) and Tokyo (+17%)